TechSmith Construction Update | February 17, 2022

February 17, 2022

1st Floor Interior framing – 95% complete ​

2nd Floor Interior Framing – 50% complete ​

Exterior – Brick is 75% complete​

Interior rough MEP (Mechanical, Electrical Plumbing). Ductwork, conduits, and piping are being installed.

Stairways are being installed.