TechSmith Construction Update
July 15, 2022
Final push on all fronts with all trades
Finish Painting on 1st & 2nd floor ongoing.
Landscaping – Started north of the parking lot and within the parking lot rain garden.
Ceiling Grid – Completed. Pads will be set once all above ceiling inspections are completed.
Elevator – 90% complete.
Oak Stair Tread installation has begun.
Data/Server room with access for MSU network engineers complete