Drywall – 98% Complete on 1st Floor
Painting on 1st floor ongoing
2nd-floor drywall – 90% complete
Drywall Finishing 65% complete on 2nd floor
Exterior Glass Curtain Wall – Began to install on 4/25/22 at North elevation
2nd-floor patio – light-weight concrete topping has been poured and currently waterproofing the concrete deck