Slab on metal deck – complete
Exterior cold form framing – complete
Interior rainwater piping complete on 2nd floor. 90% complete on the 1st floor
Interior framing underway – 50% complete on 1st floor
1st layer of roof 75% complete – this will provide weather tight system at the roof