TechSmith Construction Update

December 17, 2021

The patio was poured on 12/10/2021.​

Steel is complete – Crain is being demobilized this week.​

Exterior cold form framing is ongoing. Exterior framing will be complete by 12/24​.

Exterior insulated metal wrap panels have begun. West elevation complete. Currently working on the North elevation. ​