TechSmith Construction Update 9/13/2021

POSTED: Tuesday, September 28, 2021

CATEGORY: TechSmith Construction

Phase II

•Parking lot prepped for curb and asphalt

•1st floor underground utilities to prepare for slab on grade concrete

•Poured 1st floor slab on grade from column line 2-9

•Completed building water tie in with MSU